What happened
The House of Commons Energy Security and Net Zero Committee published its report Revisiting the nuclear roadmap on 20 November 2026, after more than 50 pieces of written evidence and five evidence sessions with 20 witnesses. As Amber Rolt reported for BusinessGreen, the MPs want the government to set out a new plan for nuclear power.
The committee's main points:
- No clear strategy. The government has not recommitted to the 2024 Civil Nuclear Roadmap, which aimed for 24 GW of nuclear by 2050. A witness told the committee that Sizewell B, Hinkley Point C, Sizewell C and the three Rolls-Royce small modular reactor (SMR) units add up to just above 9 GW.
- A new roadmap. The government is relying on the Strategic Spatial Energy Plan, first due in 2026 and now expected in early 2027. The committee wants an updated nuclear roadmap within six months of that plan, with deployment targets for large reactors, SMRs and advanced modular reactors.
- A higher target for Great British Energy-Nuclear. The public body is tasked with 2 final investment decisions by 2029; the committee wants 3 by the end of this Parliament.
- Supply chains and skills. It says the commitment to 70% UK content in the SMR programme is not enforceable enough and asks for stronger contract terms.
- Costs on bills. It says the Regulated Asset Base model used for Sizewell C moves significant construction risk to consumers, asks for more openness on the costs borne by households and businesses, and urges caution before using bill-funded models again.
- Waste. It wants a preferred site for the geological disposal facility for radioactive waste chosen before the end of this Parliament.
By convention, the government aims to respond to a select committee report within two months.
What it means for your business
Your electricity bill already carries a share of Sizewell C. Since December 2025 every licensed electricity supplier in Great Britain has paid a nuclear RAB levy for each MWh it supplies. The committee quotes the National Audit Office: about £4 on a typical household bill in 2025-26, building to a peak of around £19 to £21 a year in the plant's first decade of operation. It says DESNZ has not assessed how the cost is split between households, commercial and industrial users, which is why it wants more openness.
EMR Settlement's latest figures show an in-period adjustment: the rate for October to December 2026 goes from £3.75 to £5.15 per MWh (about 0.52p per kWh) from 6 December, then £3.68 for January to March 2027. An illustrative business using 10,000 kWh in a month would carry £37.54 of levy at the old rate, £51.51 at the adjusted one and £36.76 at the January rate, if its supplier passes it through at cost. Fixed price contracts may already include an estimate. We explained how the levy works in our Sizewell C story.
Your carbon figures don't change. The same 10,000 kWh is 1.31 tonnes CO2e of location-based Scope 2 on the 2026 grid factor of 0.13096 kg CO2e per kWh. New nuclear plants, which the committee describes as low-carbon because they emit no greenhouse gases while generating, would bring future grid factors down only once they run.
What to do now
- Check your contract for how policy costs such as the nuclear RAB levy are passed through, and whether the December rise will show on your bill.
- Keep monthly kWh from your bills, so you can check pass-through charges and report Scope 2 accurately.
- If you supply the nuclear sector, read the report's supply chain chapter: the committee wants clearer UK content rules for the SMR programme.