What happened
Louise Haigh, the First Secretary of State, gave the keynote speech at the CBI's annual conference on 23 November 2026. Much of it was about "public control" of essential services, but a large part was about the cost of energy for business. Her words: "We have the highest industrial energy prices among advanced economies."
- The gap with Europe: she said UK industrial electricity prices were around 23% above the median for the EU14 and the UK in 2008, and more than double it by 2025. She said one in four British manufacturers have moved production abroad or are seriously considering it because of energy prices, and cited CBI research that cutting industrial energy costs by 20% would unlock £130 billion of output.
- Costs off the bill: she pointed to the Renewables Obligation costs already moved off bills, the Budget decision to scrap the planned Gas Shipper Obligation levy (both funded by the Exchequer instead), and a commitment to a new Cost Control Framework.
- A system for users: prioritising cheap, clean power and electrification, faster grid connections for factories, hospitals, homes and data centres, and building generation where the network can use it. She said bill payers spent £2 billion last year switching off wind farms while paying to switch on gas plants elsewhere.
- Breaking the gas link: "Clean power producers should not earn windfall returns simply because gas is expensive," she said. The stated aim is bills in line with European counterparts by the middle of the next decade.
- A deadline now: she said 10,000 manufacturers can take up to £40 per MWh off their bills through the British Industrial Competitiveness Scheme, and that applications close in one week.
She also named the Environment Agency, Natural England, Ofwat and the Drinking Water Inspectorate as arm's length bodies already under review, and said the Cunliffe recommendations will be the starting point for a Water Bill with a single water regulator.
What it means for your business
Most of this is direction, not a new rule. No new price, levy or date was set in the speech apart from the reminder about the scheme deadline. Breaking the link between gas and electricity prices and the Cost Control Framework would need further decisions before they change a bill.
The one thing with a date is the scheme. The British Industrial Competitiveness Scheme exempts eligible manufacturing sites in Great Britain from the Renewables Obligation and Feed-in Tariff costs on their electricity from April 2027, and from Capacity Market costs from October 2027. A site needs a Companies House registration, an eligible SIC code, eligible products made at the site and at least 33 MWh of grid electricity a year.
A worked example. A factory using 500 MWh of grid electricity a year, fully exempt, would be looking at roughly £17,500 to £20,000 a year on the government's indicative £35 to £40 per MWh, which is subject to final scheme design. Its carbon footprint does not change: 500,000 kWh on the 2026grid electricity factor of 0.13096 kg CO2e per kWh is 65.48 tonnes CO2e of Scope 2 either way. A cheaper kWh changes the cost of electrifying a gas process, not the emissions of the kWh you already use.
Electrification is the thread. The speech repeatedly tied lower bills to using more electricity: "the surest route to net zero is electricity people can afford to use." If power prices fall relative to gas, swapping a gas boiler, oven or kiln for an electric one gets cheaper to run, and that is where the carbon saving comes from.
What to do now
- Manufacturers: check the scheme this week. Run the government's eligibility checker, gather a year of meter readings for each site, then apply on gov.uk before 11:59pm on 30 November 2026. Applications can't be changed once sent. You may be eligible; the scheme decides from the full application.
- Keep kWh by site. The scheme, your energy contracts and your carbon report all need the same figure: grid electricity by site, by year.
- Price an electric option. If you run gas heat, cost the electric alternative at today's prices and again at a lower power price. It shows how close the switch is.